Data Binding and Editing

TitleStartEnd
CollapseSoftware Development02/21/202007/04/2020
 CollapseScope02/21/202002/26/2020
   Determine project scope02/21/202002/21/2020
   Secure project sponsorship02/21/202002/22/2020
   Define preliminary resources02/22/202002/25/2020
   Secure core resources02/25/202002/26/2020
   Scope complete02/26/202002/26/2020
 CollapseAnalysis/Software Requirements02/26/202003/18/2020
   Conduct needs analysis02/26/202003/05/2020
   Draft preliminary software specifications03/05/202003/08/2020
   Develop preliminary budget03/08/202003/12/2020
   Review software specifications/budget with team03/12/202003/12/2020
   Incorporate feedback on software specifications03/13/202003/13/2020
   Develop delivery timeline03/14/202003/14/2020
   Obtain approvals to proceed (concept, timeline, budget)03/15/202003/15/2020
   Secure required resources03/15/202003/18/2020
   Analysis complete03/18/202003/18/2020
 CollapseDesign03/18/202004/05/2020
   Review preliminary software specifications03/18/202003/20/2020
   Develop functional specifications03/20/202003/27/2020
   Develop prototype based on functional specifications03/27/202004/02/2020
   Review functional specifications04/02/202004/04/2020
   Incorporate feedback into functional specifications04/04/202004/05/2020
   Obtain approval to proceed04/05/202004/05/2020
   Design complete04/05/202004/05/2020
 CollapseDevelopment04/08/202005/07/2020
   Review functional specifications04/08/202004/08/2020
   Identify modular/tiered design parameters04/09/202004/09/2020
   Assign development staff04/10/202004/10/2020
   Develop code04/11/202005/01/2020
   Developer testing (primary debugging)04/16/202005/07/2020
   Development complete05/07/202005/07/2020
 CollapseTesting04/08/202006/13/2020
   Develop unit test plans using product specifications04/08/202004/11/2020
   Develop integration test plans using product specifications04/08/202004/11/2020
  CollapseUnit Testing05/07/202005/28/2020
    Review modular code05/07/202005/14/2020
    Test component modules to product specifications05/14/202005/16/2020
    Identify anomalies to product specifications05/16/202005/21/2020
    Modify code05/21/202005/24/2020
    Re-test modified code05/24/202005/28/2020
    Unit testing complete05/28/202005/28/2020
  CollapseIntegration Testing05/28/202006/13/2020
    Test module integration05/28/202006/04/2020
    Identify anomalies to specifications06/04/202006/06/2020
    Modify code06/06/202006/11/2020
    Re-test modified code06/11/202006/13/2020
    Integration testing complete06/13/202006/13/2020
 CollapseTraining04/08/202006/10/2020
   Develop training specifications for end users04/08/202004/10/2020
   Develop training specifications for helpdesk support staff04/08/202004/10/2020
   Identify training delivery methodology (computer based training, classroom, etc.)04/08/202004/09/2020
   Develop training materials05/07/202005/28/2020
   Conduct training usability study05/28/202006/03/2020
   Finalize training materials06/03/202006/06/2020
   Develop training delivery mechanism06/06/202006/10/2020
   Training materials complete06/10/202006/10/2020
 CollapseDocumentation04/08/202005/20/2020
   Develop Help specification04/08/202004/08/2020
   Develop Help system04/22/202005/13/2020
   Review Help documentation05/13/202005/16/2020
   Incorporate Help documentation feedback05/16/202005/20/2020
   Develop user manuals specifications04/08/202004/09/2020
   Develop user manuals04/22/202005/13/2020
   Review all user documentation05/13/202005/15/2020
   Incorporate user documentation feedback05/15/202005/17/2020
   Documentation complete05/20/202005/20/2020
 CollapsePilot03/18/202006/24/2020
   Identify test group03/18/202003/19/2020
   Develop software delivery mechanism03/19/202003/20/2020
   Install/deploy software06/13/202006/14/2020
   Obtain user feedback06/14/202006/21/2020
   Evaluate testing information06/21/202006/24/2020
   Pilot complete06/24/202006/24/2020
 CollapseDeployment06/24/202007/01/2020
   Determine final deployment strategy06/24/202006/25/2020
   Develop deployment methodology06/25/202006/26/2020
   Secure deployment resources06/26/202006/27/2020
   Train support staff06/27/202006/28/2020
   Deploy software06/28/202007/01/2020
   Deployment complete07/01/202007/01/2020
 CollapsePost Implementation Review07/01/202007/04/2020
   Document lessons learned07/01/202007/02/2020
   Distribute to team members07/02/202007/03/2020
   Create software maintenance team07/03/202007/04/2020
   Post implementation review complete07/04/202007/04/2020
  Software development template complete07/04/202007/04/2020

The DevExpress ASP.NET Gantt (ASPxGantt) allows you to modify tasks and their dependencies, and assign or re-assign tasks' resources. Use the control's settings (GanttEditingSettings) to enable users to perform add, delete, and update functions.

Users can edit cell values in the Task List or use the chart's context menu, dialog or another chart UI to manage tasks and their properties. The component saves changes on the server and updates the chart.

The Gantt stores a user's changes and supports the 'undo' and 'redo' shortcuts (Ctrl+Z and Ctrl+Y).

Data Binding

The ASPxGantt cotrol can operate only in bound mode. It supports standard data source types, including SqlDataSource, ObjectDataSource, XmlDataSource, AccessDataSource, and SiteMapDataSource.

The control requires separate data sources for tasks (TasksDataSourceID), resources (ResourcesDataSourceID), resource assignments (ResourceAssignmentsDataSourceID), and dependencies (DependenciesDataSourceID). Mappings (ASPxGantt.Mappings) specify which field in the data source corresponds to an object's property (task, dependency, resource).