Strip Lines

TitleStartEnd
CollapseSoftware Development02/21/202107/04/2021
 CollapseScope02/21/202102/26/2021
   Determine project scope02/21/202102/21/2021
   Secure project sponsorship02/21/202102/22/2021
   Define preliminary resources02/22/202102/25/2021
   Secure core resources02/25/202102/26/2021
   Scope complete02/26/202102/26/2021
 CollapseAnalysis/Software Requirements02/26/202103/18/2021
   Conduct needs analysis02/26/202103/05/2021
   Draft preliminary software specifications03/05/202103/08/2021
   Develop preliminary budget03/08/202103/12/2021
   Review software specifications/budget with team03/12/202103/12/2021
   Incorporate feedback on software specifications03/13/202103/13/2021
   Develop delivery timeline03/14/202103/14/2021
   Obtain approvals to proceed (concept, timeline, budget)03/15/202103/15/2021
   Secure required resources03/15/202103/18/2021
   Analysis complete03/18/202103/18/2021
 CollapseDesign03/18/202104/05/2021
   Review preliminary software specifications03/18/202103/20/2021
   Develop functional specifications03/20/202103/27/2021
   Develop prototype based on functional specifications03/27/202104/02/2021
   Review functional specifications04/02/202104/04/2021
   Incorporate feedback into functional specifications04/04/202104/05/2021
   Obtain approval to proceed04/05/202104/05/2021
   Design complete04/05/202104/05/2021
 CollapseDevelopment04/08/202105/07/2021
   Review functional specifications04/08/202104/08/2021
   Identify modular/tiered design parameters04/09/202104/09/2021
   Assign development staff04/10/202104/10/2021
   Develop code04/11/202105/01/2021
   Developer testing (primary debugging)04/16/202105/07/2021
   Development complete05/07/202105/07/2021
 CollapseTesting04/08/202106/13/2021
   Develop unit test plans using product specifications04/08/202104/11/2021
   Develop integration test plans using product specifications04/08/202104/11/2021
  CollapseUnit Testing05/07/202105/28/2021
    Review modular code05/07/202105/14/2021
    Test component modules to product specifications05/14/202105/16/2021
    Identify anomalies to product specifications05/16/202105/21/2021
    Modify code05/21/202105/24/2021
    Re-test modified code05/24/202105/28/2021
    Unit testing complete05/28/202105/28/2021
  CollapseIntegration Testing05/28/202106/13/2021
    Test module integration05/28/202106/04/2021
    Identify anomalies to specifications06/04/202106/06/2021
    Modify code06/06/202106/11/2021
    Re-test modified code06/11/202106/13/2021
    Integration testing complete06/13/202106/13/2021
 CollapseTraining04/08/202106/10/2021
   Develop training specifications for end users04/08/202104/10/2021
   Develop training specifications for helpdesk support staff04/08/202104/10/2021
   Identify training delivery methodology (computer based training, classroom, etc.)04/08/202104/09/2021
   Develop training materials05/07/202105/28/2021
   Conduct training usability study05/28/202106/03/2021
   Finalize training materials06/03/202106/06/2021
   Develop training delivery mechanism06/06/202106/10/2021
   Training materials complete06/10/202106/10/2021
 CollapseDocumentation04/08/202105/20/2021
   Develop Help specification04/08/202104/08/2021
   Develop Help system04/22/202105/13/2021
   Review Help documentation05/13/202105/16/2021
   Incorporate Help documentation feedback05/16/202105/20/2021
   Develop user manuals specifications04/08/202104/09/2021
   Develop user manuals04/22/202105/13/2021
   Review all user documentation05/13/202105/15/2021
   Incorporate user documentation feedback05/15/202105/17/2021
   Documentation complete05/20/202105/20/2021
 CollapsePilot03/18/202106/24/2021
   Identify test group03/18/202103/19/2021
   Develop software delivery mechanism03/19/202103/20/2021
   Install/deploy software06/13/202106/14/2021
   Obtain user feedback06/14/202106/21/2021
   Evaluate testing information06/21/202106/24/2021
   Pilot complete06/24/202106/24/2021
 CollapseDeployment06/24/202107/01/2021
   Determine final deployment strategy06/24/202106/25/2021
   Develop deployment methodology06/25/202106/26/2021
   Secure deployment resources06/26/202106/27/2021
   Train support staff06/27/202106/28/2021
   Deploy software06/28/202107/01/2021
   Deployment complete07/01/202107/01/2021
 CollapsePost Implementation Review07/01/202107/04/2021
   Document lessons learned07/01/202107/02/2021
   Distribute to team members07/02/202107/03/2021
   Create software maintenance team07/03/202107/04/2021
   Post implementation review complete07/04/202107/04/2021
  Software development template complete07/04/202107/04/2021


This demo illustrates how to use strip lines to highlight different times in the GanttExtension. The Gantt stores strip lines (StripLine class instances) in its StripLines collection. You can specify a title (Title) and appearance settings (CssClass) for each StripLine object.

Use the Start property to specify an individual strip line or combine it with the End property setting to specify a time interval.

To highlight the current time, set the ShowCurrentTime property to true in the GanttStripLineSettings object. Use the CurrentTimeUpdateInterval property to specify the time interval between the current time updates.